Page 11 - OpenAccess-April-2021
P. 11

TECHNICAL PAPER



         Table 1: Cathodic Charge required to passivate steel at the chloride levels and current densities shown

          Current Density (mA/m ) 2                          30                                    50
             -
          % Cl  in Mortar                     1              2               3              2              4
          Cathodic Charge (kC/m )             15            120             190             74            108
                           2
         reduced as some anode systems fail, monitoring equipment   multiplied by time) delivered to the steel until passivation of the
         become antiquated and lack of adequate maintenance makes   steel was achieved increased with the level of chloride but was
         the systems inoperable with the average service life of any CP   lower at the higher current density of 50 mA/m , as summarised
                                                                                                     2
         system falling to 15 years  [19] . Inevitable additional costs are   in Table 1.
         involved in maintaining and prolonging correct operation of
         the system. It appears that there is a requirement by structure   Passivity of the steel was assumed when the 24-hour depolarised
         managers and owners for simpler CP systems which will involve   potential had reached -150mV vs Ag/AgCl, 0.5M KCl (-141mV vs
         less maintenance and monitoring requirements.          SCE) as indicated in EN 12696: 2016  [10] .
         ISO EN 12696:2016  [10]  has clear performance criteria that need   As revealed in the introduction, work by Pedefferri  [25]  and
         to be continuously satisfied to ensure that the system is working.   Presuel-Monreno et al.  [26]  had demonstrated that passivity of
         A much-used criterion is that a depolarisation potential of 100   the steel can be maintained in a corrosive environment for
         mV should be achieved when the system is temporarily turned   considerable periods, by a process they termed Cathodic
         off for a period of 24 hours. The standard also defines that a   Prevention, by applying a current density of 0.4-2 mA/m . Even
                                                                                                            2
         successful CP system either passivates the steel or reduces the   constant exposure to highly corrosive environments could
         corrosion rate of the steel reinforcement which implies, correctly,   not initiate corrosion at a current density of 1 mA/m 2 [27] . Once
         as shown earlier, that achieving 100 mV of polarisation does   corrosion is arrested, it would appear reasonable to suggest
         not necessarily mean that corrosion has been arrested short-  that a second stage of a process, based on Cathodic Prevention,
         term. Nonetheless, it has been shown in several cases that if   is likely to protect the steel from further corrosion. Thus, a CP
         a CP system is running for an extended period, e.g. 5 years,   system based on a Two-Stage process appears to be a viable
         and is then turned off, corrosion of the steel does not reinitiate   corrosion mitigation method.
         over a significant time period  [20] . As briefly mentioned earlier,
         this phenomenon is believed to be caused by some secondary   This understanding formed part of a process that has enabled
         effects, primarily, the increase in alkalinity and reduction in   the recent development of a simple to install and operate
         chloride concentration at the steel/concrete interface  [21]  which in   Two-Stage Corrosion Mitigation system  [28,29]  as illustrated in
                          -
         effect reduces the [Cl ]/[OH ] ratio considerably below the critical   Figure 16.
                               -
         ratio for initiation or maintenance of corrosion. It has also been
         suggested that realkalisation of the acidified pits occurs which   A field trial on a real structural element, a column underneath a
         allows steel repassivation within them  [22] . Once repassivation of   bridge in the UK (Figure 17), was performed which demonstrated
         the steel is achieved, the application of cathodic prevention can   the effectiveness of the system.
         then maintain the passive conditions long-term  [23] .
                                                                All cracked and spalled concrete that had occurred on two
         It was soon realised that a system that can arrest steel corrosion   edges of the column had been removed and repaired with an
         relatively early and can then switch to cathodic prevention   appropriate repair mortar. A total of six anodes were installed
         mode over the longer term is realistically possible. It was   in a grid formation at a spacing of 600 mm in such a way so
         important, however, to identify the desired current density   as to surround the repaired areas. Two silver/silver chloride
         and overall charge delivery to the steel reinforcement for   standard reference electrodes were embedded within the test
         successful corrosion arrest to occur before the current density is   areas in-between the anodes to enable monitoring of the steel
         reduced to the lower cathodic prevention current density levels   potentials both during application of the current and following
         (0.4-2 mA/m ) which have been shown to be easily achieved by   disconnection. A junction box connected the anodes to the
                   2
         galvanic anodes  [14,23] .                             steel externally, so disconnection of the anodes, either the ICCP
         To develop a viable Stage-1 procedure in which corrosion arrest   component or the galvanic component,was possible at any
         of corroding steel can be achieved, a series of experiments were   stage. The main results are detailed in Figure 18. The range of
         conducted, the results of which are published elsewhere  [24] .   current densities applied either during Stage-1 (ICCP anodes) or
         What was discovered was very interesting. At two constant   Stage-2 (galvanic anodes) is indicated at the top of the graph.
                                        2
                            2
         current levels, 30 mA/m  and 50 mA/m , the corrosion of pre-  All potentials shown are 24-hour depolarised potentials, i.e. the
         corroded steel plates in mortars containing increasing doses   current was interrupted for 24 hours before the steel potential
         of chloride by weight of cement as NaCl, was arrested after a   was recorded. The anodes were disconnected for two longer
         length of time under polarisation. The required charge (current   periods starting at 130 days and 260 days to allow extended


      68    THE INDIAN CONCRETE JOURNAL | APRIL 2021
   6   7   8   9   10   11   12   13   14   15   16